Section 9 Summary of Coordination and Environmental Compliance
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
9-5
As a result of the SFWMD’s experience during the construction of STA ¾,
including the associated bridge construction on US 27, in working with those
utilities located on the west side of US 27, it is not anticipated that substantial
relocations of utilities will be required to construct this project.
9.3 CIRCULATION OF REVISED DRAFT PIR / EIS
The Revised Draft EIS is anticipated to be released in February 2006. It will be
circulated for a minimum of 45 days after noticing in the Federal Register.
Copies of the Revised Draft EIS will be mailed to appropriate Federal and State
agencies, Native American Tribes, Environmental groups, interested public, as
well as persons whom had commented on the draft EIS. Public libraries in the
project will be provided copies to maintain in the reference section of the
libraries. The Revised Draft EIS will also be posted electronically for web
viewing. A public meeting is anticipated to be held in March 2006 to receive
comments on the Revised Draft PIR/EIS.
9.4 COMMENTS RECEIVED AND RESPONSES
Several comments were received in response to the Draft EIS. A matrix of the
comments and responses, as well as copies of the correspondence, has been
provided in Annex H.
9.5 COMPLIANCE WITH ENVIRONMENTAL LAWS, STATUTES AND
EXECUTIVE ORDER
The following documents the compliance with applicable environmental laws,
statutes, or executive orders (E.O.) and the coordination that has been completed
with respect to those laws. Letters of correspondence with appropriate agencies
is included in Annex A and Annex H, as applicable. The following descriptions
also indicate the status of any on-going or compliance issues.
In as much as construction activities on the EAA Storage Reservoir Acceler8
Project are scheduled to begin in December 2005 in accordance with the schedule
for the State of Florida’s Acceler8 program, SFWMD will be responsible for
obtaining permits issued under the authority of Section 404 of the Federal Clean
Water Act. The Acceler8 design, although similar to the PIR, will address
impacts, benefits, and compliance with environmental regulations through the
Section 404 permitting process with the USACE Regulatory Division. SFWMD
will also be responsible for obtaining the Section 401 (Clean Water Act) water
quality certification or waiver of water quality certification, as appropriate, from
the State of Florida. Typically, water quality certification is obtained through
the State of Florida’s regulatory program established under the authority of
Chapter 373, Florida Statutes. Section 402 (National Pollutant Discharge
Elimination System, a.k.a. “NPDES”) permits required under the Clean Water