Section 5 Formulation of Alternative Plans
EAA Storage Reservoirs Revised Draft PIR and EIS February 2006
5-23
this alternative would be lands between the Miami Canal and North New River
Canal, west and north of Compartment A. Of the remaining 30,500 acres
required, the SFWMD owns approximately 900 acres and the State of Florida
owns approximately 1,520 acres. The remaining lands comprising approximately
28,080 acres would have to be acquired from private interests. A portion of the
lands within the alternative were part of the original property of the “Talisman”
exchange/acquisition. There are over 35 separate ownerships. It is estimated 20
to 24 parcels would have to be acquired by condemnation.
5.3.10.2 Alternative 3
Approximately 38,000 acres would be required for the Alternative 3. This
alternative would use the entire footprint of Compartment A, comprised of
approximately 31,500 acres owned by SFWMD. All remaining lands required for
this alternative would be lands between the Miami Canal and North New River
Canal, west and north of Compartment A. Of the remaining 6,500 acres
required, the SFWMD owns approximately 900 acres and the State of Florida
owns approximately 1,470 acres. The remaining lands comprising approximately
4,130 acres would have to be acquired from private interests. A portion of the
lands within the alternative were part of the original property of the Talisman
exchange/acquisition. It is likely all of this approximately 4,130 acres would
have to be condemned.
5.3.10.3 Alternatives 4, 5, and 6
Alternatives 4, 5, and 6 are within the footprint of Compartment A, owned by
SFWMD and part of the Talisman acquisition.
5.3.10.4 Acquisition and Construction Assumptions
Table 5-8 indicates the results of the varied construction periods, due to land
acquisition requirements, of the alternatives.
TABLE 5-8: IMPLEMENTATION ASSUMPTIONS AND SCHEDULE OF
CONSTRUCTION.
Alternative Total Acres
Additional Acres
Needed
Land Certification
Schedule
Construction
Schedule
Alt 2 62,000 30,500 June 2011 Dec 2014
Alt 3 38,000 6,500 June 2009 Dec 2012
Alt 4 and 5 32,000 0 March 2007 Oct 2010
Alt 6 26,500 0 March 2007 Oct 2010